Project-Progress
Dedication of the bells 24-02-2013
Installing the new accoustic floor w/c 18-02-2013
Installing the base beems 29-01-2013
Base beams are delivered to Stone 28-01-2013
Installing the new mesh floor 14-01-2013
Casting the concrete pad stones 18-12-2012
The new stays and 3 of the new wheels are delivered to the Bell Foundry 10-12-12
The first new wheel is constructed 29-11-2012
Len visits the Bell Foundry 23-11-2012
Cutting out the frame pockets 16-11-2012
Bells go to London 29-10-2012
Third and Fourth return to Gloucester 22-10-2012
Removing the bells 16-10-2012
Opening the bell moulds 28-09-2012
Casting of the new bells 21-09-2012